Forest Oaks Community Pool
Project Type:
Capital Project
Project Status:
Under Review
Background - Forest Oaks Community Pool Facility
- The Forest Oaks Community Pool facility and concrete deck areas are not ADA compliant & need to be brought into compliance.
- Forest Oaks Pool facility is not ADA compliant in any portion of the building, made of CMU block walls with brick veneer, not easy to bring into compliance
- Also has old wiring and plumbing, uses too much energy, is outdated, and the pool needs replastering
- Almost entire patio area is out of ADA compliance – built to drain water & has too much slope
- Estimated to remodel existing facility and patio area approximately: $900,000 to $1,000,000
Alternatives - Forest Oaks Community Pool Facility
- Demolish structure & baby pool, add new prefab building, correct concrete deck areas, replaster existing pool, add small splash pad, repair parking area, replace back fence, add shade covers
- Demolish building, plaster pool, add pre-fab building, concrete deck removal & replacement $381,000
- Demo baby pool and add small splash pad $190,000
- Parking lot repairs, trash enclosure $ 30,000
- Back deck shade covers $ 40,000
- Concrete fence along Evers Road $ 25,000
- Engineering, etc. $110,687
- Total $761,787