Leon Valley Community Pool
Project Type:
Capital Project
Project Status:
Under Review
Background - Leon Valley Community Pool Facility
Leon Valley Community Pool facility concession, restrooms, and a portion of patio not in compliance with ADA
- Building, concrete deck areas, and parking lot are outdated and not ADA compliant;
- Building and pool are costing more and more each year in maintenance and utilities;
- The pool needs replastering now;
- The estimated cost to remodel the existing building and concrete deck areas is $150,000 - $180,000, and the pool replastering would be $82,000, a total of $262,000.
Alternatives - Leon Valley Community Pool Facility
Could demolish structure and pool, then reconfigure entire site, including the vacant lot at Peachtree/Poss.
Cost estimates:
- Pool area – demolition, new pool, buildings, patio, fencing, lighting, landscape, irrigation = $2,500,000
- Splashpad = $750,000
- Parking lot = $255,000
- Engineering, additional services = $595,850
- Total = $4,100,850